Didcot Biomethane Project Commissioned – Southern Gas Networks (SGN) 150 150 Technica Ltd

Didcot Biomethane Project Commissioned – Southern Gas Networks (SGN)

Technica Limited were responsible for the Design Coordination and Commissioning of the first Bio-methane to Grid system at Didcot, working on behalf of SGN Major Projects & Construction. The containerised solution provides the analysis and conditioning of the gas prior to injection into the grid, typically the system comprises:

  • FWACV / GS(M)R Analyser System including Test Gases
  • Custody Transfer Flow Metering & Flow Computer
  • Supervisory Control System – (SCS)
  • Odorant Injection System
  • ESD Shutdown System
  • Pressure Reduction System
  • FWACV Supervisory Control System
  • Gas Quality PC
  • Flow Computer
  • High Integrity PLC/ESD System
  • Telemetry & Communications equipment
  • DC Power Distribution
  • Hazardous Area Galvanic Isolators
  • Third Party Signals and Repeats

Other equipment such as a UPS and electrical distribution together with process instrumentation for monitoring purposes.