TECHNICA COMPLETES IMPORTANT CONTRACT AHEAD OF SCHEDULE 780 410 Technica Ltd

TECHNICA COMPLETES IMPORTANT CONTRACT AHEAD OF SCHEDULE

Having been awarded a contract to upgrade the Fire and Gas System at Huntingdon Compressor Station by National Grid Capital Delivery Team on 1 February 2017, we are pleased to announce completion of the project installation and commissioning ahead of schedule.

The project, which saw Technica design, build, install and commission the system, has achieved formal Operational Acceptance by National Grid over 5 weeks ahead of schedule.  Of note, Technica were commended for their excellent safety performance having completed over 5300 hours on this project without any health and safety incident or observations.

Managing Director and Owner of Technica, John Davison commented that “this achievement is down to the hard work and dedication of our fantastic team here at Technica and our partners within National Grid”.  He continued “We are delighted to be able to complete the project ahead of schedule and delivering excellent customer service to such an important client”.

Project Engineer, Andy Smith who was instrumental in running this project said “I am pleased with the success of the project and our achievement.  We look forward to providing an excellent service to National Grid in the future”.

Business Development Director, Richard Law stated that “The successful completion of this project ahead of schedule demonstrates that Technica are able to tackle complex and challenging projects, delivering a quality and effective service to our clients”.